Quantity Check
See which bid items are running over or under plan, and by how much. Up to 15 items at a time. Free, no sign-up.
An overrun means more was installed than the bid planned; an underrun means less. Enter the planned and installed quantity for each bid item and the check marks every row, with the difference in % and in units.
On plan = within ±2% of the planned quantity.
Results
What is a quantity overrun or underrun?
On a unit-price road job, each bid item has a planned quantity, such as tons of asphalt or cubic yards of excavation. An overrun is when the installed quantity is more than planned. An underrun is when it’s less. Both are common, because field conditions rarely match the plans exactly: a thicker lift, soft subgrade, a shorter curb run. What matters is catching them early, so you can check the measurements, talk to the owner or engineer, and avoid surprises when final quantities are settled.
How the % is calculated:
% difference = (installed − planned) ÷ planned × 100
Example: planned 200 TON, installed 225 TON → (225 − 200) ÷ 200 × 100 = +12.5% (+25 TON)
Status rules used here: more than +2% is ▲ Overrun, less than −2% is ▼ Underrun, anything in between is ● On plan. A row with installed quantity but no planned quantity is ○ No plan, because a % can’t be calculated.
This is a quantity comparison, not contractual or legal advice. How overruns and underruns are paid depends on your contract.
FAQ
Does this tell me whether I’ll be paid for an overrun?
No. That depends on your contract. This tool only compares the numbers.
Why ±2% for on plan?
It’s a simple default that keeps small rounding differences from showing up as flags. Your project may use a different tolerance.
Is my data saved to a project?
Your rows are saved only in this browser’s local storage. The tool doesn’t create projects or accounts. Tracking bid items through to final pay is on our roadmap.